PRO1 - TMS

Informations générales
Code: PRO1
Titre: TMS
Type: TPRO1 - Implementation
Statut: En cours
Sponsor: ENT1 - VT Supply Chain (Interne)
Réference du train: Train 1
Méteo: Moyenne
Taux avancement global estimé: 5
Taux avancement délai: 5
Date de début: 2025-06-01 00:00:00
Date de fin estimée: 2026-09-30 00:00:00
Date de fin réelle: 2026-06-06 00:00:00
Budget OPEX estimé: 200
Budget OPEX réel: 250
Budget CAPEX estimé: 300
Budget CAPEX réel: 350
Caractéristiques
CaractéristiqueNatureValeur
CARAC66 - Criticity (Texte)PropriétéNone
Contexte

OPmobility has decided to implement a central TMS (Transport Management System) solution that did not previously exist (either at the local or central level).

This solution requires process changes in the supply chain, the creation of ad-hoc department, and the implementation of an IT system supporting the entire process.

This solution will transform the transport operations’ company across Mexico, US/Canada, Europe, and the rest of the world (APAC and , South America regions).

Contributeurs
EntitéActeurRôle
ENT1 - VT Supply Chain (Interne)Courseaux DavidArchitecte domain
ADR
ADRDescription
Key results
Key resultDescriptionType
ECART1 - Key resultThis is a key resultFonctionnel
Processus
Processus
PROCESS1 - Processus
Processus: PROCESS1 - Processus
Adhérences
ProjetTypeImpact
PRO1 - TMSProjet interneImpact on itself ;-)
External project - An external projectProjet externeHas impact on TMS project
Démarche

Ceci est la démarche de mon projet

Contraintes
ContrainteDescription
PROCONT1 - ConstraintA constraint
Exigences
ExigenceTypeDescription
PROEX1Non fonctionnelleUser characteristics: Users can access the solution via a web portal from a PC, laptop, or tablet. External partners use only the web portal, while admin users have direct access (e.g., SSH).
PROEX2Non fonctionnelleLocation characteristics: The solution is intended for global deployment, with initial rollout in the following order: Mexico, US/Canada, EMEA, APAC, and SAO.
PROEX3Non fonctionnelleLoad characteristics: Shipment volume will increase over time (approx.): 100,000 in 2026, 450,000 in 2027, and 470,000 in 2028. Final figures will be refined during workshops.
Sécurité
SécuritéDescription
PROSECU2 - SEC2
PROSECU3 - SEC3
PROSECU4 - SEC4
PROSECU5 - SEC5
PROSECU6 - SEC5
PROSECU7 - SEC6
Plan d'occupation des sols impacté
Capacités
CapacitéTypeImpact
CAP156 - Analyze performanceModificationNone
Cartographie des données impactée
Objets métiers
Objet métierTypeImpact
OM6 - CustomersModificationNone
Services
ServiceTypeImpact
SERV1 - ServiceModificationNone
Solution applicative: PROSCEN1 - Applicative Solution
Description: This is the base scenario
Paysage applicatif impacté
Applications
ApplicationTypeImpact
APP954 - 4FlowModificationIntroduction of a central TMS for transport planning, execution, optimization, and freight invoice control. Consumes master and demand data from SAP/EDI, performs transport and MRP related optimization, and sends outputs back to SAP. Carrier operational systems remain out of OPMobility responsibility.
APP955 - BOOMIModificationExtension of the integration layer to orchestrate SAP–TMS exchanges. Implements new SAP interfaces (master data, invoices) using the Boomi for SAP add on where available, or custom BAPIs for Lighting.
APP952 - SAP ECC6 ExteriorModificationActivation and expansion of interfaces with the TMS ecosystem: master data exposure, exchange of MRP optimization results, integration of carrier invoices (posting and archiving), and generation of outbound logistics messages (plant-to-plant and returnable ASN).
Composants logiciels
Composant logicielTypeImpact
CLOG321 - BOOMI (BOOMI)Modificationimpact composant logiciel
Flux logiques
Flux logiqueTypeImpact
FLOG10 - Carrier invoice (BOOMI -> SAP ECC6 Exterior)Modificationimpact flux logique